Grain Storage & Logistics Project, Beidahuang Grain Logistics Co., Ltd, Shandong, China
● MEC (Mechanical, Electrical & Control Equipment and Installation) project
● 60,000 Tons silos
● Ship unloading: 600 t/h x2
● Truck loading: 300 t/h x2
General Situation
Construction of 10 steel grain silos and supporting works (including office buildings)
Storage Capacity
60 thousand tons of all and 6000 tons for each silo.
Scale
Large-scale comprehensive project general contracting project, including civil construction, equipment procurement, installation, commissioning, training services to the inspection and acceptance of turnkey projects.
The expansion and reconstruction project is difficult to construct. The total duration is only 195 days.
Project innovation and significance
To create a new road of comprehensive general contracting business and establish long-term cooperation with the Beidahuang group.